We next prepared for the electrician (pre-mounting of electrical boxes, excavation of outside wiring, etc.). He began his work on May 13.
Next came the plumbing. Fern installed the wastewater pipes first and then the water supply lines.
Then came the insulation. We have chosen to insulate just the ceiling (for the alleviation of noise from the metal roof as well as for thermal protection).
Vapour barrier was then installed. After passing an inspection, we installed drywall on the ceiling. The walls are next.
In between the major projects outlined above, we also installed railings for the new clubhouse access decking and a new attic access door.
What's Next?
The next few weeks will be just as busy as the past few weeks. The
next step will be drywalling the walls and then installing flooring. Light
fixtures, ceiling fans, receptacles and switches will come after that.
Then work on the kitchen and bathrooms will begin. Once that's all done,
we should finally be eligible for our occupancy permit. Adding trim boards
and painting will be last of all.
Thank You!
We extend our sincerest gratitude to all who offered additional clubhouse
funding this spring, and to all who have volunteered their help with the
physical work so far this year. Neither our clubhouse nor Naturist Legacy
Park itself would exist without the generous funding and active volunteering
of club members. Thank you!
SOURCE: This article is as it appeared on the Naturist Legacy website on June 23, 2014. I am the author.